Multiple Choice
A tracking Gantt chart does NOT show:
A) the reason an activity has slipped.
B) which activities are ahead of schedule.
C) which activities are on schedule.
D) which activities are behind schedule.
Correct Answer:

Verified
Correct Answer:
Verified