Earned Value Is

Question 89

Multiple Choice

Earned value is:


A) the total budget for the project.
B) a cost estimate of the budgeted resources across the project's life cycle.
C) the real budgeted value of the work that has actually been performed to date.
D) the cumulative total costs incurred in accomplishing the various project work packages.

Correct Answer:

verifed

Verified