    Use the Data to Calculate the Earned Value for the Project
Solved

Use the Data to Calculate the Earned Value for the Project

Question 94

Question 94

Multiple Choice

Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.   A)  $38,500 B)  $46,550 C)  $56,750 D)  $61,125


A) $38,500
B) $46,550
C) $56,750
D) $61,125

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q30: The one factor that earned value management

Q52: Earned value management jointly considers the impact

Q57: If the actual cost line on an

Q58: The earned value to date divided by

Q62: It is possible to measure:<br>A)only positive deviations

Q89: Use the S-curve to choose the best

Q90: The project costs plotted against the elapsed

Q90: The Project Implementation Profile includes this critical

Q102: In earned value management analysis,the cumulative amount

Q108: If significant deviations from the project plan

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines