    In Earned Value Management Analysis,the Cumulative Amount of the Budget
Solved

In Earned Value Management Analysis,the Cumulative Amount of the Budget

Question 102

Question 102

Multiple Choice

In earned value management analysis,the cumulative amount of the budget becomes the:


A) planned value.
B) scheduled value.
C) cost basis.
D) cost driver.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q17: What are any four benefits to using

Q23: Identify a different key success driver and

Q53: What is earned value management and how

Q62: Gap analysis refers to any measurement process

Q98: A tracking Gantt chart:<br>A)monitors costs and budget

Q99: Milestones are generally considered to be:<br>A)demotivators for

Q103: Of the three classic metrics of project

Q104: Use the earned value table for Project

Q105: Earned value management allows a project manager

Q107: A(n)_ identifies the stage of completion each

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines