Multiple Choice
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's model to determine the aggregated one sigma buffer for this project.
A) 20 days
B) 10 days
C) 15 days
D) 5 days
Correct Answer:

Verified
Correct Answer:
Verified
Q23: The Central Limit Theorem says that if
Q32: Which tendency is not a contributing factor
Q32: If people believe that they built extra
Q35: Both positive and negative variation are usually
Q36: Use these activity durations (that have been
Q37: In applying the principle of common cause
Q55: Project personnel often become involved in several
Q61: The student syndrome of wasting extra safety
Q63: Why aren't both negative and positive project
Q79: Define and describe the function and interrelationship