Multiple Choice
A resource constraint can be exploited using CCPM methodology by:
A) determining the priority among projects for access to the drum.
B) scheduling each project to start based on the drum schedule.
C) designating the critical chain as the chain from the first use of the constraining resource to the end of the project.
D) resolving any conflicts if the creation of the capacity constraint buffers adversely affects the drum schedule.
Correct Answer: