Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 72

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 45 days? A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 45 days?   A)  $222,667 B)  $243,675 C)  $258,333 D)  $272,500


A) $222,667
B) $243,675
C) $258,333
D) $272,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions