Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 40 days?
A) $242,667
B) $255,600
C) $263,333
D) $272,500
Correct Answer:

Verified
Correct Answer:
Verified