Multiple Choice
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?
A) 17
B) 12
C) 13
D) 26
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q8: Activity Z has estimates a = 5,b
Q15: The late start time should be calculated
Q16: Based on the activity network pictured, what
Q20: Phoebe B. Beebee is constructing a canal
Q22: Use the network diagram and activity lengths
Q23: Use the network diagram and activity lengths
Q69: What are three methods of duration estimation
Q71: Serial activities are those that:<br>A)flow from one
Q93: Negative float exists when a project's critical
Q95: Thanks to excessive dilly dallying,the subcontractor grossly