menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    What Is the Early Finish Time for Activity F Given
Solved

What Is the Early Finish Time for Activity F Given

Question 21

Question 21

Multiple Choice

What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?   A)  17 B)  12 C)  13 D)  26


A) 17
B) 12
C) 13
D) 26

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Activity Z has estimates a = 5,b

Q15: The late start time should be calculated

Q16: Based on the activity network pictured, what

Q20: Phoebe B. Beebee is constructing a canal

Q22: Use the network diagram and activity lengths

Q23: Use the network diagram and activity lengths

Q69: What are three methods of duration estimation

Q71: Serial activities are those that:<br>A)flow from one

Q93: Negative float exists when a project's critical

Q95: Thanks to excessive dilly dallying,the subcontractor grossly

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines