Multiple Choice
If a functional manager will not release the resources you need as project manager,your best course of action is to:
A) adjust project schedules and priorities accordingly.
B) try to negotiate for partial assistance.
C) notify top management of the consequences.
D) update your resume.
Correct Answer:

Verified
Correct Answer:
Verified