Multiple Choice
The Analytical Hierarchy Process is used to decide among three projects that we'll call A,B,and C.The total score for project A is .650,for project B is .514,and for project C is .321.Which of the following statements is best?
A) Project A is twice as good as project C.
B) The analysis must be incorrect because the total scores should sum to 1.00.
C) The analysis must be incorrect because there are two total scores that exceed 0.50.
D) The analysis must be incorrect because project C's total score is odd.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Successful project management firms rely on home
Q24: Describe or define any four important attributes
Q26: What are options models and when should
Q31: Net present value is being used to
Q37: A project manager is using the internal
Q40: One method of assigning weights to the
Q42: Successful firms use project portfolio planning routinely
Q43: A project selection model that is broad
Q48: The simplest method of project screening and
Q69: Souder's project screening criterion of realism addresses