Scope Management Typically Involves Which of the Following Processes

Question 31

Multiple Choice

Scope management typically involves which of the following processes?


A) acquiring, developing and managing the project team
B) ensuring that the project includes all the work required and only the work required, to complete the project successfully
C) collecting, disseminating and storing appropriate project information
D) identifying, analyzing and controlling project risks

Correct Answer: