Multiple Choice
Project managers and teams should consider risks in the project charter for all the following reasons EXCEPT:
A) risks that may have a negative impact on project objectives should be identified and addressed.
B) to eliminate all project risks before the project charter is signed
C) a risk that may have a positive impact on the project should be addressed by a plan to capitalize upon it.
D) risks that may have a positive impact on the project create opportunities.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Describe and contrast the roles played by
Q15: In a project charter,acceptance criteria:<br>A) are often
Q16: Quality control standards are the criteria,including performance
Q17: Within the project charter,the scope overview accomplishes
Q20: When developing the milestone schedule for the
Q21: Which of the following charter elements should
Q21: A background statement is a mandatory element
Q22: Within the project charter,the scope overview:<br>A) identifies
Q23: Describe how you might use lessons learned
Q27: The signing of the project charter signals