    A Common Tool Project Teams Use Is a Responsibility Assignment
Solved

A Common Tool Project Teams Use Is a Responsibility Assignment

Question 39

Question 39

Multiple Choice

A common tool project teams use is a responsibility assignment matrix (RAM) .Typically,this chart will depict:


A) the date each activity will begin.
B) the duration of each activity.
C) the roles key members of the team will play on each activity.
D) organizational reporting structure

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q10: When determining resource availability,project managers need only

Q17: Describe how crashing and fast tracking can

Q24: When recruiting resources to support a project,it

Q34: What should a project manager's considerations be

Q34: RACI (Responsible,Approve,Consult,Inform)charts go beyond a communication plan

Q36: When project managers include diverse perspectives in

Q38: Project managers often confront the challenge of

Q42: The process of estimating the types and

Q44: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project

Q44: When identifying people to work on the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines