Multiple Choice
Project managers must often face the challenge of compressing the project schedule. All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
A) Reduce the project scope.
B) Overlap sequential activities using finish-to-finish relationships.
C) Use the float in critical path activities
D) Partially overlay sequential activities using time leads.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Often circumstances dictate the need to accelerate
Q7: Scope reductions are fairly common among projects
Q10: When determining resource availability,project managers need only
Q12: When constructing a responsibility matrix or "RACI"
Q14: The project resource allocation plan is the
Q15: Project managers often confront the challenge of
Q16: While a "RACI" chart may be very
Q20: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2247/.jpg" alt=" Figure 8-1 RACI
Q44: When identifying people to work on the
Q44: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project