Multiple Choice
Below is a spreadsheet designed to calculate the project completion time.Use the spreadsheet to answer the following question(s) .
-What is the early finish time for Activity O?
A) 95
B) 129
C) 113
D) 97
Correct Answer:

Verified
Correct Answer:
Verified