Multiple Choice
Below is a spreadsheet designed to calculate the project completion time.Use the spreadsheet to answer the following question(s) .
-Which of the following formulas is used to compute the slack for an activity?
A) latest start - activity time
B) latest finish - early finish
C) latest finish - activity time
D) latest start - early start
Correct Answer:

Verified