Multiple Choice
All of the following accurately describe earned value management EXCEPT:
A) It is used to objectively measure project performance and progress.
B) It enables a project team to understand progress in terms of both cost and schedule.
C) It is good for performance reporting but not for forecasting
D) It is in essence a decision-making tool.
Correct Answer:

Verified
Correct Answer:
Verified