Figure 141 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31

Question 29

Multiple Choice

  Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)  -Consider the project performance report presented in figure 14.1.What valid conclusion can you draw regarding the project schedule performance as of October 31,20XX?​  A)  The project is $18,000 behind schedule.  B)  The project is $26,000 behind schedule.  C)  The project is 18 days behind schedule.  D)  The project is $26,000 ahead of schedule. Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)
-Consider the project performance report presented in figure 14.1.What valid conclusion can you draw regarding the project schedule performance as of October 31,20XX?​ 


A)  The project is $18,000 behind schedule. 
B)  The project is $26,000 behind schedule. 
C)  The project is 18 days behind schedule. 
D)  The project is $26,000 ahead of schedule.