Multiple Choice
Melinda is assigned a task on Monday that needs to be completed by Friday.She decides to begin the task on Thursday as she estimates that the task will take her two days to complete,but the task will take her three days.This underestimation of how long it will take to complete a task is called:
A) self-handicapping.
B) impact bias.
C) planning fallacy.
D) spotlight effect.
Correct Answer:

Verified
Correct Answer:
Verified
Q35: Which of the following is true of
Q36: Which of the following statements on self-concept
Q37: The fact that we usually attribute more
Q38: Which of the following terms denotes what
Q39: A study by Gilovich et al.(2000)had college
Q41: The illusion that our concealed emotions leak
Q42: In the context of the dual attitude
Q43: Who among the following most likely belongs
Q44: Benjamin is able to alter his behaviors
Q45: Talia,a project manager,estimates that a project will