Multiple Choice
An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the variance of the activity?
A) 4.17
B) 25.17
C) 17.36
D) 10.33
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q65: A(n)_ is a point when an activity
Q67: An activity has an optimistic time estimate
Q68: The overall effect of laddering activities is
Q69: Summaries for some subsets of the activities
Q71: Serial activities are those that:<br>A)flow from one
Q73: Use the information in the table to
Q74: What is the float start time for
Q84: Consider a project composed of activities X
Q89: Discuss any five approaches to reducing the
Q100: What is the underlying theory to the