    An Activity Has an Optimistic Time Estimate of 15 Days,a
Solved

An Activity Has an Optimistic Time Estimate of 15 Days,a

Question 70

Question 70

Multiple Choice

An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the variance of the activity?


A) 4.17
B) 25.17
C) 17.36
D) 10.33

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q65: A(n)_ is a point when an activity

Q67: An activity has an optimistic time estimate

Q68: The overall effect of laddering activities is

Q69: Summaries for some subsets of the activities

Q71: Serial activities are those that:<br>A)flow from one

Q73: Use the information in the table to

Q74: What is the float start time for

Q84: Consider a project composed of activities X

Q89: Discuss any five approaches to reducing the

Q100: What is the underlying theory to the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines