Activity-Based Costing and Bottom-Up Budgeting Share the Step Of

Question 3

Multiple Choice

Activity-based costing and bottom-up budgeting share the step of:


A) identifying cost drivers associated with each activity.
B) identifying activities that consumer resources and assigning costs to them.
C) assigning costs to projects by multiplying the cost driver rate times the volume of units.
D) tending to overestimate project costs due to the lack of involvement by top management.

Correct Answer: