Multiple Choice
A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.2,a complexity risk of 0.6,and a dependency risk of 0.9.The probability of failure is:
A) less than or equal to 0.3.
B) greater than 0.3 but less than or equal to 0.6.
C) greater than 0.6 but less than or equal to 0.9.
D) greater than 0.9.
Correct Answer:

Verified
Correct Answer:
Verified
Q48: The PRAM model for risk management proposes
Q53: Sketch the risk level and opportunity curves
Q53: To protect his poultry from meteorites,the gentleman
Q55: The probability that a project to establish
Q57: Each project team member had a backup
Q59: One source of information on future risks
Q60: The greatest project risk occurs when:<br>A)the probability
Q62: Risk and opportunity:<br>A)both increase throughout the project
Q63: At each phase,the project risk analysis and
Q82: PRAM (project risk analysis and management)should be