Multiple Choice
It was well known that the cost of failure category for cost was a 0.7,and for schedule was a 0.8.The project team settled on the cost of failure for reliability of 0.6,and for performance of 0.4.What is the overall consequence of failure?
A) less than or equal to 0.5
B) greater than 0.5 but less than or equal to 0.6
C) greater than 0.6 but less than or equal to 0.7
D) greater than 0.7
Correct Answer:

Verified
Correct Answer:
Verified
Q11: The PRAM model for risk management proposes
Q21: The amount a company has at stake
Q22: _ is defined as the art and
Q24: Early in the life cycle of a
Q28: A common method of transferring the risk
Q29: One phase of the project risk analysis
Q30: Which of these statements about the project
Q45: Opportunity emerges from favorable project circumstances and
Q46: What is the relationship between a project's
Q52: What is the PRAM methodology and what