Multiple Choice
The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below.What is the overall risk factor for the project?
A) less than or equal to 0.6
B) greater than 0.6 but less than or equal to 0.7
C) greater than 0.7 but less than or equal to 0.8
D) greater than 0.8
Correct Answer:

Verified
Correct Answer:
Verified
Q4: With the failure probability and consequence scores
Q5: There is always a chance that different
Q10: The terpsichorean was familiar with the risks
Q12: Risk management is a:<br>A)three-stage process.<br>B)four-stage process.<br>C)five-stage process.<br>D)six-stage
Q13: A serious risk factor probably has:<br>A)a high
Q14: The expected cost of an item that
Q27: One approach to risk mitigation is simply
Q43: How do mentoring and cross-training mitigate risk?
Q46: Technical risk is the probability that the
Q64: What are the two types of contingency