Multiple Choice
The project team's office needed a revolving door to facilitate the influx and outflow of personnel.Team members needed name tags to keep track of who was who and what their duties were.The project was jeopardized by:
A) poor leadership.
B) high turnover.
C) lack of team motivation.
D) poor communication among team members.