Multiple Choice
When work is organized into cost control accounts:
A) the work no longer needs to be tracked by the project manager.
B) the subdeliverables become cost centers instead of profit centers for the project.
C) these are assigned to the units performing project activities.
D) these budgets can then be assigned back to the project manager's department.
Correct Answer:

Verified
Correct Answer:
Verified