Multiple Choice
A project manager can identify personnel who will be directly responsible for each task in the project's development by using a(n) :
A) responsibility assignment matrix.
B) milestone designation chart.
C) Merrill report.
D) work package report.
Correct Answer:

Verified
Correct Answer:
Verified