Multiple Choice
Projects are often underfunded in the concept stage because:
A) the project requirements were deliberately understated.
B) there is complete trust in project managers by top management so more resources can be asked for at any time.
C) the project's goals are too clearly defined.
D) the project's top management sponsor is too influential.