Multiple Choice
Souder's project screening criterion that indicates an effective model must reflect organization objectives,including a firm's strategic goals and mission is called:
A) realism.
B) capability.
C) comparability.
D) ease of use.
Correct Answer:

Verified
Correct Answer:
Verified