Question 38

Multiple Choice

A writer estimates it will take three months to generate spiffy documents to accompany a seminal work in operations management.He grossly underestimates the time required and misses his deadline by two months.This estimate was:


A) objective and accurate.
B) subjective and accurate.
C) objective and inaccurate.
D) subjective and inaccurate.