Multiple Choice
Between projects A and B,project A will be considered a superior financial undertaking if it has:
A) a shorter payback period than project B.
B) a lower average rate of return than project B.
C) a lower net present value than project B.
D) a longer payback period than project B.
Correct Answer:

Verified
Correct Answer: