A Project Manager Is Using the Net Present Value Method

Question 90

Multiple Choice

A project manager is using the net present value method to make the final decision on which project to undertake.The company has a 10% required rate of return and expects a 4% rate of inflation for the following five years.What is the NPV of a project that has cash flows as shown in the table? A project manager is using the net present value method to make the final decision on which project to undertake.The company has a 10% required rate of return and expects a 4% rate of inflation for the following five years.What is the NPV of a project that has cash flows as shown in the table?   A) $264,252 B) $324,606 C) $442,242 D) $398,780


A) $264,252
B) $324,606
C) $442,242
D) $398,780

Correct Answer: