Multiple Choice
A project that is exceptionally risky might still be undertaken by a firm if they have several other projects underway that are considered more of a sure thing.This approach to project selection is best described by the criterion called:
A) strategic "fit."
B) risk.
C) desire for portfolio balance.
D) top management pressure.
Correct Answer:

Verified
Correct Answer: