Cleland's Project Stakeholder Management Cycle

Question 28

Multiple Choice

Cleland's project stakeholder management cycle:


A) requires all stakeholders to be identified and locked in as a first step.
B) is used to identify only internal stakeholders.
C) is used to identify only external stakeholders.
D) is a recurring cycle that allows new stakeholders to be considered at any time.

Correct Answer:

verifed

Verified