Multiple Choice
The difference between a BOT contract and a BOOT contract is that under the BOOT contract:
A) the customer must observe all phases of the project process before the product is handed over.
B) the project organization is obligated to complete the project on time.
C) the project organization must take initial ownership of the product.
D) the customer must organize the project's resources for the project organization.
Correct Answer:

Verified
Correct Answer:
Verified