Question 9

Multiple Choice

Which of these is NOT a consequence of a natural process for project closeout?


A) Team members suffer a natural let-down and are de-motivated to participate in future projects.
B) Managers can create a database of lessons-learned analyses.
C) Closeout can serve as an important source of information for team members.
D) Structure for a systematic and complete project shut-down arises.