Multiple Choice
Which of these is NOT a sign of pending IT project failure?
A) Best practices and lessons learned are ignored.
B) Project managers don't understand users' needs.
C) Wireless technology is relied on too heavily.
D) Project changes are poorly managed.
Correct Answer:

Verified
Correct Answer:
Verified