Multiple Choice
When a project is shut down,the project team must ensure that all relevant stakeholders are clearly aware of the project shut down,including the date by which all activities will cease.This is an:
A) intellectual and internal issue.
B) emotional issue of the project team.
C) emotional issue of the clients.
D) intellectual and external issue.
Correct Answer:

Verified
Correct Answer:
Verified