An ex-gratia claim made when a project is closed down is made when:
A) there is no contractual basis for a claim.
B) the project company fails to perform to the terms of the contract.
C) the client company fails to perform to the terms of the contract.
D) a third party causes either the client or project company to fail to perform to the terms of the contract.