Use the S-curve to choose the best statement about the project it describes.The horizontal axis is in weeks.
A) More time passes from weeks 5 to 10 than from weeks 20 to 25.
B) More time passes from $50,000 to $60,000 than from $5,000 to $10,000.
C) More money is spent from weeks 0 to 10 than from weeks 30 to 40.
D) The total amount spent on the project at the end of the 40th week is approximately $110,000.