Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement.
A) The project never experiences negative variance.
B) With regards to budget,the project starts badly but finishes well
C) With regards to budget,the project starts well but finishes badly.
D) The project is in a constant state of positive variance.
Correct Answer:

Verified
Correct Answer:
Verified