Take the Factors Considered by Earned Value Analysis and Subtract

Question 33

Multiple Choice

Take the factors considered by earned value analysis and subtract those considered by tracking Gantt charts.The factor(s) you have remaining are:


A) cost.
B) cost and schedule.
C) schedule and performance.
D) performance.

Correct Answer: