Multiple Choice
Use the data to calculate the schedule performance index for the project for the end of week 10.All amounts are in thousands of dollars.
A) 1.24
B) 0.93
C) 0.81
D) 0.76
Correct Answer:

Verified
Correct Answer:
Verified