A recurring problem with establishing accurate or meaningful EVM results has to do with:
A) the 0/100 rule.
B) over-reliance on the S-curve.
C) the need to recognize the human factor.
D) the need to satisfy stakeholders within budget and time parameters.
Correct Answer:

Verified