A project that must be finished by December 31st is:


A) time-constrained.
B) resource-constrained.
C) mix-constrained.
D) capacity-constrained.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q39: Because resource management is typically a multivariate,combinatorial

Q42: The problem of resource underutilization that a

Q55: The idea behind resource leveling is to

Q63: Describe resource leveling;its objectives and the basic

Q66: The project represented by this resource load

Q68: _ an activity means interrupting the continuous

Q70: Use the information in the table and

Q71: A resource loading form is also known

Q73: Once Pussy Galore's Flying Circus had put

Q91: If an activity can be split,only the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines