Multiple Choice
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements?
A) day 21
B) day 18
C) day 24
D) day 15
Correct Answer:

Verified
Correct Answer:
Verified