Multiple Choice
Splitting activities refers to:
A) assigning the work to two or more workers.
B) assigning the work to two or more days.
C) starting an activity,interrupting it to use a resource elsewhere,and then returning to work on the activity.
D) breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor.