Multiple Choice
All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 20% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.Much to his surprise,top management leaves his project alone.How much of a cushion is now built into the project?
A) 73%
B) 60%
C) 140%
D) 44%
Correct Answer:

Verified
Correct Answer:
Verified
Q28: What is aggregated buffer and how can
Q37: In applying the principle of common cause
Q38: Critical Chain Project Methodology _ risk for
Q39: A(n)_ refers to a safety margin separating
Q43: A system-wide constraint is called a:<br>A)rope.<br>B)resource.<br>C)drum.<br>D)chain.
Q45: A project consists of three activities with
Q46: Your usual twenty minute commute takes two
Q47: Which of the following is an example
Q66: Once the organization elevates its constraint,its system
Q75: What are the implications for due dates