A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology?
A) 48
B) 32
C) 64
D) 43.5
Correct Answer:

Verified
Correct Answer:
Verified
Q26: The root cause of overinflated time estimates
Q27: In classic project management,activity durations are estimated
Q28: Create and solve an example of at
Q30: What is the student syndrome and what
Q32: If people believe that they built extra
Q32: A feeder buffer is a buffer that
Q34: In order to resolve a resource conflict,it
Q35: Which tendency is NOT a contributing factor
Q36: Describe three ways that project members routinely
Q72: An important element in critical chain scheduling